Nicollet County Public Works:

Mathiowetz Construction is currently on track to have CR 15 reconstructed (except from CR 19 to CR 40) and back to a gravel surface by late October 2023. The portion of CR 15 from CR 19 to CR 40 will have the existing pavement left in place over the winter. The reconstruction of this segment will begin in 2024. The detour that is currently in place will remain over the winter. In 2024 concrete paving, signing, and final turf establishment will be completed on the entire segment, with the road anticipated to be reopened to through traffic in September 2024.

In late July, Holtmeier Construction completed the installation of a 12’ X 9’ box culvert. The new culverts replaced the failing 66” and 90” concrete culverts. The pictures to the left show the project area before and after construction.

 