MnDOT Hosting Open Houses

MnDOT Hosting Open Houses

MANKATO, Minn. – The Minnesota Department of Transportation is holding two construction open houses for a project on Highway 4 from St. James to Sleepy Eye in preparation for construction expected to begin in mid-April, weather permitting. The public is invited to attend in Sleepy Eye on Wednesday, April 10 from 4 to 6 p.m. at the Community Center, 115 2nd Avenue NE, or in St. James on Monday, April 15 from 4 to 6 p.m. at the Watonwan County Library, 125 Fifth Street S.

Staff from MnDOT and the contractor will be available to provide more information about the project and answer questions. There is no formal presentation planned, and attendees are welcome to arrive anytime.

The Highway 4 project between St. James to Sleepy Eye includes roadway, bridge, and drainage improvements. In addition to resurfacing approximately 25 miles of roadway, three bridges will be replaced. Additionally, the improvements made to the road will allow Highway 4 from St. James and Sleepy Eye to become a 10-ton route.

Construction on the project is expected to begin in mid- April and continue until early October, weather permitting.  Traffic will be detoured during construction. Visit the project website for detour information.

Ulland Brothers, Inc. was awarded the project with a bid of $18,884,550.58.

Stay connected

 

MnDOT invites and encourages participation by all.  If you need an ASL, foreign language interpreter, or other reasonable accommodation, or need documents in an alternative format (such as braille or large print), please email your request to Janet Miller at adarequest.dot@state.mn.us or call 651-366-4720.

Construction open houses for Hwy 4 Sherburn to St. James project

MnDOT is holding two construction open houses for a project on Hwy 4 from Sherburn to St. James in preparation of construction expected to begin in late April, weather permitting.

The public is invited to attend in Trimont on Tuesday, April 9 from 4 to 6 p.m. at Triumph Hall, 546 Main Street E, or in Sherburn on Thursday, April 11 from 4 to 6 p.m. at the Senior Dining Center, 21 East 1st Street.

Staff from MnDOT and the contractor will be available to provide more information about the project and answer questions. There is no formal presentation planned, and attendees are welcome to arrive anytime.

The Hwy 4 project between Sherburn and St. James includes roadway, bridge, and drainage improvements. In addition to resurfacing approximately 25 miles of roadway, the bridge over Cedar Run will be replaced and multiple bridges will be repaired. Pedestrian accommodations in the cities of Sherburn and Trimont will also be improved.

Construction on the project is expected to begin in late April and continue until late August, weather permitting.  Traffic will be detoured during construction. Visit the project website for detour information.

OMG Midwest was awarded the project with a bid of $20,724,636.58.